May 11 2020

Staff received notice from GM Blue Plan

Staff received notice from GM Blue Plan regarding their recommendation of the closure of the Riversdale Bridge on May 11, 2020. This recommendation was approved by Council on May 12, 2020.

May 12 2020

Council Approved Closure

Staff received notice from GM Blue Plan regarding their recommendation of the closure of the Riversdale Bridge on May 11, 2020. This recommendation was approved by Council on May 12, 2020.

October 22 2020

Project Notification

On October 22, 2020 the Historic Saugeen Metis, Great Lakes Metis Council, Saugeen First Nation, Saugeen Ojibway Nation and the Chippewas of Nawash Unceded First Nation were notified of the Notice of Project Initiation and the Public Information Centre Virtual Meeting. 

On October 22, 2020 a Notice of Project Initiation and information regarding the Public Information Centre Virtual Meeting was sent to residents surrounding the Riversdale Bridge.

On October 22, 2020 and October 29, 2020 a Notice of Project Initiation and information regarding the Public Information Centre Virtual Meeting was published in the Hanover Post and the Walkerton Herald Times.

October 29 2020

Project Notification

On October 22, 2020 and October 29, 2020 a Notice of Project Initiation and information regarding the Public Information Centre Virtual Meeting was published in the Hanover Post and the Walkerton Herald Times.

November 09 2020

Public Information Meeting Held

The Municipality of Brockton is advancing project specific planning to address the deteriorated condition of Bridge No.2 (Greenock) on Bridge Street in Riversdale, just north of Highway 9. The Municipality has identified advanced deterioration of the superstructure and substructure, including severe section loss in the floor beams and significant corrosion of the concrete and steel elements throughout. As a result, the bridge was recently closed to all traffic. The project is being planned under Schedule ‘B’ of the Municipal Class Environmental Assessment (EA), as outlined in the Municipal Class EA Manual prepared by the Municipal Engineers Association (2015).

Alternative solutions that were considered for the structure included the following:

1. Do Nothing;
2. Rehabilitate the Existing Bridge;
3A. Replacement with a Single-Lane Structure;
3B. Replacement with a Two-Lane Structure;
4. Bridge Removal; and
5. Bridge Retention/Adaption.

Due to COVID-19 restrictions, this meeting was held virtually using Zoom video conferencing. You can watch the public meeting here: Public Information Session, November 9th, 2020.

 

November 23 2020

Public Comments Closed

November 23, 2020 was the final day to submit public comments.  

February 09 2021

Council Report

On February 9, 2021 GM Blue Plan presented to Council regarding the Riversdale Bridge findings and a recommendation based on these findings. Council decided to move forward with replacing the bridge, however whether the bridge will be replaced with a one or two lane structure will be determined at a later date.

March 23 2021

Council Report

On March 23, 2021 Brockton Council decided to replace the Riversdale with a two lane structure as per the recommendation from GM Blue Plan

April 01 2021

Notice of Completion

On April 1, 2021 GM Blue Plan issued the Notice of Completion of the Municipal Class Environmental Assessment. This notice initiates a 30 day comment period where interested persons may provide written comment to our team below. Please read the Notice of Completion for more information on the commenting period.

May 03 2021

Notice of Completion Commenting Period Ends

May 3, 2021 is the final day to submit comments as per the Notice of Completion commenting period.

November 23 2021

Council Report

Council received a report from staff requesting confirmation as to which type of bridge structure will be tendered.

Council approved a prefabricated Steel Panel Bridge to be tendered in 2022.

May 10 2022

Council Approved Awarding the Tender

Council approved awarding the tender to Looby Builders out of Dublin in the amount of $2,634,178.31 including HST.